New Zealand International Convention Centre project consists of 5 stages.

STAGE 1 COMPLETE: 4 x MSSBs

Stage 1 is complete with the build and delivery of x Mechanical Services Switchboards (MSSBs) to power the carpark mechanical services.

STAGE 5 COMPLETE: 1 x 1 MSSB

Stage 5 is complete with the build and delivery of 1 x MSSB that services the chillers for both NZICC and the Horizon Hotel.

STAGE 4 IN PROGRESS:

- 1 of 8 MSSBs delivered

STAGES 2 - 4 IN PROGRESS

We have 12 MSSBs remaining to build for this project. We look forward to continuing our work on NZICC rebuild and delivering quality boards and service throughout the remaining stages 2,3 and 4.